Nighttime construction shows improved traffic for daytime commutes and faster construction speed for Plano, according to public works officials.
Drew Zaeske, the public works community investment program manager, provided a presentation about nighttime construction in the city at a meeting Nov. 23.
In a nutshell
Zaeske said the city had two pilot locations for nighttime construction, including concrete replacement at Custer Road and Legacy Drive and along Park Boulevard between Preston Road and Ohio Drive. He said the locations were determined with the following conditions in mind:
Arterial roadways and major intersections
Commercial and industrial zones
500-foot buffer for residential areas
Concrete panel replacement, not removal
Working hours from 9 p.m.-5 a.m.
Fast-setting concrete to allow next-day traffic on the pavement
Dig deeper
Zaeske said work at the first location took four days, and public works estimated the work would have taken two weeks if it were done in the daytime. He said the second location had a larger construction zone and took eight weeks for completion, close to the same as if it were done in the daytime.
"There's a ton of driveways that tie in [to the second zone] and so we really didn't want to be shutting down driveway approaches to all the businesses in the area," Zaeske said.
Both locations still had two lanes open during the daytime, which improved traffic, Zaeske said, and costs for the projects ended up close to the same as if they were done in the day.
The city also kept track of any resident feedback on noise. He said there was one accident at each location with inattentive drivers.
"The level of disruption, when you talk about the driveways, minimizing that impacts local businesses," City Manager Mark Israelson said. "We think that if we're able to do this in a way that is more efficient and it has less disruption to daily commutes, businesses and things of that nature, that that is maybe a non-financial benefit, but one nonetheless."
The background
This year's set of night construction work started in July. The projects are part of a citywide effort to replace concrete roads at main roads, per previous reporting.
The city piloted its first set of nighttime construction projects in 2025. Zaeske said asphalt overlays throughout the city have been done through nighttime construction since 2021.
The city applies an emulsion layer over newly replaced concrete before setting its asphalt overlay, per previous reporting. The city's current method of asphalt overlays is expected to last 15 years before needing replacement.
Looking ahead
The city completed concrete repair along Communications Parkway, McDermott Road, Custer Road and Coit Road in 2026. Sections of those streets and a portion of Alma Drive will be up for nighttime construction asphalt overlays in 2027, per previous reporting. Asphalt overlay projects are scheduled through 2034.
The city is also planning concrete rehabilitation projects for parts of Hedgcoxe Road, Legacy Drive, Ohio Drive and Park Boulevard for 2027.