Learn more about three future Hutto road improvement projects in varying stages of development.
CR 137 and FM 1660 S.
Project: The project includes construction of additional lanes and a roundabout at the intersection of CR 137 and FM 1660.
Update: Right-of-way acquisition, which is the purchase of property to widen the road, was completed in April.
- Timeline: TBD
- Cost: $11.2 million
- Funding source: Hutto Economic Development Corp.
CR 163 reconstruction
Project: Design and reconstruct CR 163 from FM 1660 to the cemetery driveway.
Update: Hutto City Council approved a supplemental agreement for additional surveying, easement acquisition and appraisals and subsurface utility engineering investigations in June.
- Timeline: TBD
- Cost: $5.1 million for construction
- Funding source: TBD
Carl Stern and FM 685
Project: The project will include construction of a right-turn lane at the westbound approach of Carl Stern Drive at the intersection of FM 685.
Update: The contractor submitted 60% design plans to the city for review in June.
- Timeline: TBD
- Cost: TBD
- Funding source: TBD