Both Pflugerville and Hutto are in the midst of planning and construction for several road projects. Read more about each below.
Upcoming projects
1. Kelly Lane Phase 3
Project: The road will be widened to four lanes from Moorlynch Avenue to Weiss Lane. The project also includes the construction of four roundabouts and pedestrian improvements, according to the city.
Update: City staff and the consultant met with officials from the Federal Emergency Management Agency on Sept. 11 to review the first round of comments on the project's flood risk map.
Timeline: completion expected in September 2028
Cost: $32 million
Funding source: city of Pflugerville
2. Carl Stern and FM 685 intersection improvements
Project: The project will include construction of a right-turn lane at the westbound approach of Carl Stern Drive to the intersection of FM 685.
Update: The contractor submitted full design plans to the city for review in September.
Timeline: TBD
Cost: $2 million
Funding source: city of Hutto
Ongoing projects
3. Immanuel Road widening
Project: The project includes full reconstruction and widening of the existing roadway to three lanes from Pecan Street to Killingsworth Lane. Improvements include curb and gutter, intersection improvements, street lighting, underground storm infrastructure and shared-use paths.
Update: Construction was slated to begin on Oct. 6.
Timeline: October 2026-January 2028
Cost: $28 million
Funding source: city of Pflugerville
4. Kelly Lane intersection improvements
Project: The project consists of dedicated left-turn lanes, U-turn lanes and signal modifications. Once completed, both frontage roads will have two straight lanes, two left-turn lanes with one acting as a turnaround lane combination and one right-turn lane.
Update: City Council approved the construction contract with Joe Bland Construction on Aug. 11. Construction began in early October.
Timeline: October 2026-March 2027
Cost: $2 million
Funding source: city of Pflugerville
5. Parkway Drive reconstruction
Project: The road will be reconstructed with pavement, curb, drainage, sidewalk and streetlight improvements.
Update: Construction began in mid-September.
Timeline: September 2026-July 2027
Cost: $3.4 million
Funding source: city of Pflugerville
6. CR 137 and FM 1660 intersection improvements
Project: The project includes construction of additional lanes and a roundabout at the intersection of CR 137 and FM 1660.
Update: A change order added $26,768 in funding for a school walkway in August.
Timeline: completion expected in April
Cost: $9.1 million
Funding source: Hutto Economic Development Corp.