About 150,000 gallons of domestic wastewater overflowed at the Barry Rose Water Reclamation Facility in Pearland the morning of April 21.
The spill is estimated to have happened between 6:15- 8 a.m. at the facility, located at 1902 Barry Rose Road, Pearland, according to a news release shared by the city of Pearland.
The spill is being attributed to a delayed alarm notification caused by a power surge at the facility following the storms the morning of April 21. According to the release, staff were able to contain the spill to the facility's grounds so it would not impact Clear Creek.
The impacted area is restricted to the reclamation facility. The untreated wastewater is being pumped back into the facility, and property grounds are being disinfected by staff to remove any potential contamination according to the release.