The estimated cost of the Mykawa Road widening project has increased to $123.7 million, including a 206% increase in Pearland's local funding contribution, following council approval of an amendment to the project budget at its Nov. 19 meeting.
What’s new
The amendment increases the project's total estimated cost to $123.7 million to reflect the current estimated costs for engineering design, right-of-way acquisition and construction, city documents show.
Under the agreement, Pearland covers 20% of the project costs, while the Texas Department of Transportation provides the remaining 80%, documents show.
The approved changes include:
While the project budget has increased since its initial estimates, projects typically don’t see significant cost increases after this stage, unless construction costs rise before the project’s actual letting date, City Manager Trent Epperson said.
Some context
The Mykawa Road project will widen nearly 3 miles of roadway between Broadway Street and Beltway 8, expanding the existing two-lane road into a four-lane divided boulevard with new storm drainage, traffic signals, landscaping and a 10-foot shared-use path, as previously reported by Community Impact.
Looking ahead
The project is in its final design phase, with right-of-way acquisitions and utility relocations expected to take place over the next 18 months, Epperson said.
The project remains on schedule to go out for bids in late 2028, with construction expected to begin in 2029 and take approximately two years to complete, documents show.