Project: One of the city’s corridor improvement programs, work along Slaughter Lane includes widening the roadway from four to six lanes, adding shared-use paths, signal upgrades and landscaping enhancements. Spanning FM 1826 to Old Lockhart Road, the project is aimed at increasing safety for pedestrians and bicyclists as well as increasing mobility.
Update: According to the city of Austin, the most recent phase of work from MoPac to Brodie Lane, known as C2, kicked off this past summer. Work includes new traffic signals and crosswalk upgrades at the intersection of Brodie Lane and Bowie High School. At Zuniga Drive, there will also be a new pedestrian crossing light and other safety improvements.
- Timeline: 2025-27
- Cost: $23 million
- Funding source: 2016 Mobility Bond, federal grant funding allocated by the Capital Area Metropolitan Planning Organization
Completed projects183 North Mobility Project northbound connector
Project: The project includes the construction of two express lanes in each direction on US 183, a general-purpose lane to bring the number of nontolled lanes to four in each direction, new shared use path connections, new sidewalks and cross-street connections for bicycles and pedestrians.