In order to stay on track for a fall 2023 completion, the Capital Metro board of directors approved an additional $750,000 in funding for the design-build contract for CapMetro’s proposed McKalla Station rail project—part of the larger Project Connect—during its meeting on May 22.
In March 2022, a $20.8 million design-build contract with civil contractor Stacy and Witbeck Inc. was approved. According to agenda documents, the contract includes the station’s platforms, canopies, accessibility, other amenities, and relocation and upsizing of a wastewater line.
During the May 22 meeting, Kenneth Cartwright, CapMetro’s vice president of facilities and construction, explained the $750,000 does not reflect an increase on the cost of the project overall, but is for the Stacy and Witbeck Inc. contract for additional work, including the relocation, design and construction of a storm sewer, and other resources to ensure the project remains on schedule.
“During the early stages of construction, we identified that our northbound platform would partially overlap a pre-existing 42-inch stormwater line that belongs to the city of Austin,” Cartwright said. “[In] working with the city, we determined that it would be best for the long-term life of that stormwater line to relocate it further to the east and put it out along the Delta Drive right of way.”