The much-maligned San Antonio Street bridge construction project is several months ahead of schedule, according to officials with the city of New Braunfels. Expected to impede traffic accessing the downtown area for an initial estimate of 16 months, there is a possibility that contractor Capital Excavation could finish the project and open the San Antonio Street bridge to vehicular and pedestrian traffic by the end of summer 2020, said Greg Malatek, New Braunfels public works director.
The San Antonio Street bridge first closed to vehicular traffic Sept. 3, and demolition began Sept. 19. The project remains on track to allow Comal River recreation beneath the bridge before Memorial Day, Malatek said.
The primary reason for the shortened timeline is the usage of precast caps and beams that will support the bridge deck, said Will Lockett, Texas Department of Transportation area engineer.
Once demolition work was complete and the original deck removed, the five 70-foot arch spans that comprise the old bridge were raised by two to three inches, Lockett said.