This month New Braunfels Utilities is slated to begin work on the nearly $5.5 million Grandview Pump Station and Discharge Line Upgrade project, which is slated to conclude in December.
On May 9 Pesado Construction Co. will begin rock sawing trench lines, according to an NBU press release, and will continue until late August.
The work will require a partial lane closure on the Loop 337 Frontage Road near H-E-B, according to the release. Additional lane closures on Kerlick Lane will also take place between May and August, but two-way traffic will continue.
“We understand this work will inconvenience many drivers in the Loop 337 Frontage Road/SH 46 and Walnut Avenue/Kerlick Lane areas and apologize for this disruption,” said Shawn Schorn, chief water engineer for NBU, in the release. “This project is part of our master plan to help ensure that the residents of New Braunfels continue to have reliable access to water for the foreseeable future, and we intend to work as quickly as possible to complete it on time and on budget.”