Update: Design work on the project is 30% completed.
- Timeline: May 2025-late 2026 (design), construction to begin in spring 2027
- Cost: $6.6 million
- Funding source: City of McKinney
2. Graves Street and First Street infrastructure reconstructionProject: A reconstruction of infrastructure, including waterlines, sanitary and storm sewer lines, and street pavement, is planned for a section of Graves Street between Greenwood Street and Harroun Avenue, as well as First Street between Graves and College streets.
Update: Design work on the project is 30% completed.
- Timeline: May 2025-late 2026 (design), construction to begin in spring 2027
- Cost: $16.3 million
- Funding source: city of McKinney
3. Infrastructure and drainage improvements for Church, Henry areaProject:
Reconstruction is planned for infrastructure, including waterlines, sewer lines, drainage infrastructure and more along various streets in East McKinney. The project boundary includes sections of Church, Davis, Henry, McKinney and Wood streets.