Lewisville City Council approved another $29 million worth of work on the Corporate Drive extension, which will create a four-lane divided highway that will provide an arterial passage from Flower Mound to Plano.
Sundt Construction had a winning bid of $29.7 million for segments four and five of the project, voted on by council during the April 16 meeting. The Irving-based company is also doing segments two and three of the Corporate Drive expansion. That was a $43 million contract awarded in December by council.
The details
Funding for the newest addition will come from the Corporate Drive capital project account. The project, which will be from east of Elm Fork Trinity River to Carrollton Parkway and Carrollton Parkway from the Sam Rayburn Tollway to Old Denton Road, will include: