With summer in full swing, several construction projects continue to make headway across the Leander and Liberty Hill area. Whether you're preparing for a road trip or your regular commute, here are 10 projects to keep in mind while planning your drive.
Check out these transportation updates from city, county and state transportation sources to plan your route.
Upcoming projects
Freedom River Parkway East and West
Project: Construction includes the creation of a new east-west roadway connection from Hwy. 29 to RM 1869 and from Bagdad Road-CR 279 to Hwy. 29, improving Liberty Hill bypass connectivity.
Update: Both projects remain in the design phase through 2026 as part of the Liberty Hill bypass connectivity network.
- Timeline: early 2027-early 2029
- Cost: East: $36.3 million; West: $61.5 million
- Funding source: Williamson County 2023 road bond
Seward Junction Loop North reconstructionProject
: Work includes the reconstruction of Seward Junction North Loop along two segments connecting US 183 to Hwy. 29, and CR 260 to CR 213.
Update: Schematic design has been completed. Construction is expected to begin this summer.
CR 201 reconstructionProject: Road improvements include the reconstruction of CR 201 from CR 200 to Umbrella Sky, including shoulders and turn lane improvements.
Update: Preliminary design is complete. Construction is expected to begin this fall.
- Timeline: fall 2026-fall 2027
- Cost: $16 million
- Funding source: Williamson County road and bridge program
CR 279-Bagdad Road improvementsProject
: Plans call for the realignment and reconstruction of CR 279-Bagdad Road from Loop 332 to CR 281 at the Leander city limits, including added lanes and a 10‑foot shared‑use path for bicyclists and pedestrians.
Update: Right of way has been acquired, utilities are being relocated, and design is expected to be completed by this summer.
- Timeline: early 2027-late 2028
- Cost: $57.3 million
- Funding source: 2019 Williamson County road bond; federal funding through the CAMPO
CR 175 wideningProject: The initiative will see CR 175 widened from south of Creek Meadow Cove to RM 2243, which is expected to improve capacity and regional connectivity.
Update: The Phase 2 preliminary design is complete, and the 100% design is expected later this year.
- Timeline: summer 2027-late 2028
- Cost: $42.8 million
- Funding source: Williamson County 2023 road bond
CR 214 extensionProject
: Work includes the construction of two bidirectional lanes that will be added to extend CR 214 from Lariat Loop-South Hemingway Loop to US 183 over the San Gabriel River.
Update: Design expected to be completed later this year.
- Timeline: summer 2027-early 2029
- Cost: $2.3 million
- Funding source: 2023 Williamson County road bond
Ongoing projectsLegacy Ranch Drive expansion
Project: Crews are working to expand approximately 0.6 miles from Seward Junction North Loop, also known as CR 258 and CR 260, to a CR 258 extension east of US 183, including new signals, pavement improvements, and turn lanes serving a future Liberty Hill ISD site.
Update: Contractors broke ground March 6.
- Timeline: March 2026-summer 2026
- Cost: $1.4 million
- Funding source: Williamson County 2023 road bond
Ronald Reagan Boulevard lane wideningProject
: The county-led project will see the widening of approximately 7 miles from FM 3405 to Hwy. 29, including separated northbound and southbound roadways.
Update: Construction is underway.
San Gabriel Parkway extensionProject
: The city-led road program will extend the San Gabriel Parkway eastward from Isaias Drive to West Ronald Reagan Boulevard, between the Palmera Ridge and Palmera Bluff subdivisions, as an arterial roadway.
Update: Construction is ongoing; a traffic signal at San Gabriel Parkway and Ronald Reagan Boulevard is expected to be operational in 2026.
- Timeline: January 2025-February 2027
- Cost: $7 million
- Funding source: city of Leander certificates of obligation bonds
RM 2243, Hero Way controlled-access highwayProject
: A substantial reconstruction and widening of RM 2243 and Hero Way is underway, which will see the two-lane roadway divided into a controlled-access highway from 183A Toll to Southwest Bypass, including frontage roads in both directions.
Update: Initial-phase construction began in late January, including frontage road work from the 183A Toll to Garey Park. Phase 2A is expected to begin in fall 2027.
- Timeline: early 2026-early 2028
- Cost: $132 million
- Funding source: Williamson County 2019 road bond