Leander and Liberty Hill area residents continue to see transportation improvements as local, county and state agencies work to accommodate rapid growth. Check out several transportation projects reshaping the flow of traffic this month, ranging from intersection designs to new roadway expansions.
Check out these transportation updates from city, county and state sources:
Ongoing projects
Legacy Ranch Drive expansion
Project: Crews are working to expand approximately 0.6 miles from Seward Junction North Loop, also known as CR 258 and CR 260, to a CR 258 extension east of US 183, including new signals, pavement improvements, and turn lanes serving a future Liberty Hill ISD site.
Update: Contractors broke ground March 6.
Ronald Reagan Boulevard lane widening
Project: The county-led project will see the widening of approximately 7 miles from FM 3405 to Hwy. 29, including separated northbound and southbound roadways. New traffic signals are operational at Ronald Reagan Boulevard and Santa Rita Boulevard.
Update: Construction is underway.
RM 2243, Hero Way controlled-access highway
Project: A substantial reconstruction and widening of RM 2243 and Hero Way is underway, which will see the two-lane roadway divided into a controlled-access highway from 183A Toll to Southwest Bypass, including frontage roads in both directions.
Update: Initial-phase construction began in late January, including frontage road work from the 183A Toll to Garey Park. Phase 2A is expected to begin in fall 2028, according to county documents.
- Timeline: early 2026-spring 2030
- Cost: $132 million
- Funding source: Williamson County 2019 road bond
Upcoming projects
Seward Junction Loop North reconstruction
Project: Work includes the reconstruction of Seward Junction North Loop along two segments connecting US 183 to Hwy. 29, and CR 260 to CR 213.
Update: Schematic design has been completed. Construction is expected to begin this summer.
CR 279-Bagdad Road improvements
Project: Plans call for the realignment and reconstruction of CR 279-Bagdad Road from Loop 332 to CR 281 at the Leander city limits, including added lanes and a 10‑foot shared‑use path for bicyclists and pedestrians.
Update: Final project designs are expected to be submitted in August while utilities are being moved.
- Timeline: early 2028-early 2030
- Cost: $57.3 million
- Funding source: 2019 Williamson County road bond; federal funding through CAMPO
CR 175 widening
Project: The initiative will see CR 175 widened from south of Creek Meadow Cove to RM 2243, which is expected to improve capacity and regional connectivity.
Update: The Phase 2 preliminary design is complete, and the 100% design is expected later this year.
- Timeline: summer 2027-late 2028
- Cost: $42.8 million
- Funding source: Williamson County 2023 road bond
CR 214 extension
Project: Work includes the construction of two bidirectional lanes that will be added to extend CR 214 from Lariat Loop-South Hemingway Loop to US 183 over the San Gabriel River.
Update: Design expected to be completed later this year.
- Timeline: summer 2027-fall 2029
- Cost: $2.3 million
- Funding source: 2023 Williamson County road bond