Liberty Hill officials gave the green light in late June to fund $933,609 to move wastewater mains as part of a project that will expand a stretch of Hwy. 29, a partnership with the Texas Department of Transportation.
Two-minute impact
TxDOT is currently finalizing plans to widen Hwy. 29 from CR 322 in Bertram to the Butler Farms subdivision to allow for the addition of a middle turn lane, city documents state. During the design process, the state determined that the city’s wastewater mains would be in the way of that project.
Because Liberty Hill built the utility lines within the state’s right of way, the city is responsible for moving them, Deputy City Manager Brandon Pritchett said. Liberty Hill City Council approved an advanced funding agreement June 24, allowing the city and state to combine the work each is responsible for into one project.