Leander City Council members unanimously voted May 7 to allocate $405,646 toward resurfacing the outer lanes of South Bagdad Road between Kettering Drive and Crystal Falls Parkway.
These improvements, which are financed through the certificates of obligation—the CO bond Series 2024-B fund balance—will resurface both the northbound and southbound outer lanes of South Bagdad Road, which have been damaged by utility trenching required by the Bagdad Terminus Station project.
The details
The city already repaved the middle lanes of South Bagdad Road between Kettering Drive and Crystal Falls Parkway due to the effects of the Bagdad Terminus Station project, which upgraded the infrastructure at Bagdad Terminus Pump Station. While the project budget originally accounted for the cost of resurfacing the middle lanes of South Bagdad Road, the city authorized additional funding to cover the costs of resurfacing the outer lanes May 7.