1. New RR 620 lane
A new auxiliary southbound lane on RR 620—from just north of Lohmans Crossing to Spillman Loop in Lakeway—will be added this summer. The project also includes adding pavement at several RR 620 intersections including Falcon Head Boulevard and Ladera Boulevard to allow a three-lane approach on the west side of the intersections. This configuration will match the east side of these intersections. Timeline: May-August Cost: $1.42 million Funding sources: Texas Department of Transportation
2. Cold Water Lane segment closure
A section of Cold Water Lane near its intersection with Top O the Lake Drive in the city of Lakeway is temporarily closed to allow storm sewer culvert work on nearby streets. Additionally, a section of Top O The Lake at the intersection is reduced to one lane, and detour signage and barricades were placed in the area March 14.
Timeline: March 21-early June Cost: $813,000 estimated Funding sources: city of Lakeway
3. Loop 360 entrance/exit lanes
The TxDOT will add extended entrance and exit lanes on Loop 360 to improve intersections with Walsh Tarlton Lane, the Barton Creek Square Mall entrance, MoPac and the intersection just south of MoPac in Austin. A left-turn lane will also be added on the northbound frontage road of MoPac at Loop 360.