Curious about which new businesses, restaurants and facilities are coming soon or underway in your backyard and beyond? Our commercial project roundup helps identify what is being built in the community. The following commercial permits have been filed recently in the Lake Travis area under the Texas Department of Licensing and Regulation. All information, including cost and timeline, is subject to change.
Fidelity Fitness Center: One Destiny Way, Westlake
Type of work: renovation/alteration
Estimated cost: $2.47 million
Timeline: May 1-Aug. 31
Scope of work: interior renovation of existing fitness center
Carbon Health, Shops at the Galleria: 12918 Shops Parkway, Ste. 100, Bee Cave
Type of work: renovation/alteration
Estimated cost: $400,000
Timeline: Aug. 15-Nov. 21
Scope of work: interior build-out of tenant suite for medical clinic
Cava: 701 S. Capital of Texas Hwy., Ste. G750, West Lake Hills
Type of work: renovation/alteration
Estimated cost: $175,000
Timeline: April 1-Sept. 1
Scope of work: interior renovation
Sculpture Garden Pedestrian Bridge: Lohmans Crossing Road and Cross Creek, Lakeway
Type of work: new construction
Estimated cost: $134,000
Timeline: June 27-Aug. 31
Scope of work: approximately 513 linear feet of 8-foot concrete trail, including 20-linear-foot pedestrian bridge over Hurst Creek
Riley’s Ranch Pet Spa: 15839 W. Hwy. 71, Bee Cave
Type of work: new construction
Estimated cost: $3 million
Timeline: May 2, 2022-May 1, 2023
Scope of work: new construction of an animal boarding facility
Westlake Entrada: 63 Tarragona Drive, Westlake
Type of work: new construction
Estimated cost: $500,000
Timeline: May 16-Sept. 16
Scope of work: tenant finish-out of a restaurant space
Lakeway Medical Village: 312 Medical Parkway, Lakeway
Type of work: new construction
Estimated cost: $3.1 million
Timeline: March 1-Dec. 15
Scope of work: tenant improvements for the first floor lobby and the second floor
Summer Moon Coffee Shop; 15511 W. Hwy. 71, Bee Cave
Type of work: new construction
Estimated cost: $325,000
Timeline: Feb. 7-Aug. 1
Scope of work: new build-out to existing building
Total Care Primary Care: 1945 Medical Drive, Ste. 150, Lakeway
Type of work: renovation/alteration
Estimated cost: $150,000
Timeline: May 1-Sept. 30
Scope of work: first time interior tenant finish-out
Watkins Insurance Group: 3500 S. FM 620, Ste. C, Bee Cave
Type of work: new construction
Estimated cost: $1.2 million
Timeline: Aug. 1-Sept. 15
Scope of work: ground-up construction, including the interior finish-out of a 4,470-square-foot building for office use