In the inaugural address for his second term in January 2020, Mayor Sylvester Turner promised Houstonians would see “noticeable improvements” in the quality of city streets by the end of 2023. By the end of his term’s first year, however, many of the street rehabilitation projects planned throughout the city had been delayed.
“There were contractor staffing shortages and supply shortages, and in the districts where projects did get completed, it was because they were already underway,” said Erin Jones, spokesperson for Houston Public Works.
Progress varied widely between districts. District D, which covers Third Ward, Sunnyside and much of South Houston, for example, saw 88 lane miles of improvements completed within the fiscal year.
District E, however, which covers the Clear Lake, Kingwood and Lake Houston areas saw 0.6 lane miles of improvements completed. The public works department originally planned to cover 28 lane miles in District E.