1. Lockwood Drive/Woodland Hills Drive expansion, extension
Harris County Precinct 2 is designing two additional phases of the project, which will expand Woodland Hills Drive to four lanes between Beltway 8 and Eagle Ridge Elementary School, where the road currently ends. A new four-lane roadway will then be constructed between Eagle Ridge Elementary and Woodland Path Drive. The project also includes a bridge over Williams Gully. Phase 1, which expanded Lockwood Drive between North Lake Houston Parkway and the Union Pacific Corp. rail line was completed in June.
Timeline: April 2015-fourth quarter 2017 Cost: $22.8 million Funding sources: Harris County precincts 1, 2 and 4; McCord Development
2. Wilson Road expansion
The expansion of Wilson Road between just north of Beltway 8 and Atascocita Road has reached the final study phase. The findings of the engineering study will be presented at a Sept. 13 Harris County Commissioners Court meeting. It was originally slated to reach the design phase in July. The project will expand the road to four lanes.
Timeline: TBA Cost: $10.2 million Funding sources: Harris County Precinct 4