1. Morton Ranch expansion
The Morton Ranch Road project from Katy Hockley Cutoff Road to Porter Road was completed in August. The road was expanded from a two-lane asphalt roadway with roadside ditches to a four-lane concrete boulevard with a 32-foot wide median and underground storm sewer system.
Timeline: completed Cost: $5.6 million Funding sources: Harris County
2. FM 1463 expansion
A project to widen FM 1463 from I-10 to FM 1093 is in development and has yet to be funded. The project would widen FM 1463 from two-lanes to four-lanes with additional lanes near I-10 and at major intersections.
Timeline: TBD Cost: $74.7 million Funding sources: Texas Department of Transportation