The Katy City Council met for its regular meeting Aug. 13 and approved by a unanimous vote an extension for the memorandum of understanding between the city, the Katy Development Authority and NOBA 171 LLC to continue development of the Katy Boardwalk Project through the end of the year. “We’d actually kind of run out of time on the previous [term of the agreement], so the extension allows us to move forward,” Mayor Pro Tem Durran Dowdle said. A memorandum of understanding, commonly referred to as an MOU, is an agreement between government entities and business partners. The Katy Boardwalk agreement lays out certain project deadlines:
- Preliminary design criteria and a site plan are due by Oct. 31.
- A nonbinding letter of intent from a hotel franchisor and a draft of the franchise agreement and a letter of intent from a hotel operator are due by Nov. 30.
- A recommended financial structure for the project, including private debt and equity and public investment for the project is due by Nov. 30.
- An estimated construction schedule is due by Nov. 30.