1. Owens Road widening and realignment project
Formerly a private prison road, Owens Road has been transferred to Fort Bend County for public use. The project will realign the west end of Owens Road to line up with Plantation Drive. A private developer will construct two additional lanes between FM 1464 and the Grand Parkway. Timeline: May-October
2. Brandt Lane extension
Preliminary plans are being made by Fort Bend County to extend Brandt Lane to connect and intersect Skinner Lane and Mason Road to alleviate traffic congestion. The county is working to secure right of way. Timeline: Early 2018 –mid-2018
3. US 90A widening project
This project will widen US 90A to add a third lane in each direction from west of Hwy. 6 in Sugar Land to the Grand Parkway near Richmond. The project is in Phase 6, which consists of placing an asphalt overlay on US 90A. A sound wall will also be constructed. Timeline: estimated completion date of October 2017 Cost: $9.98 million Funding sources: Texas Department of Transportation
4. Intersection of US 90A and FM359
This project is in Phase 2 of five phases to construct an elevated intersection to eliminate the FM 359 grade crossing with the Union Pacific Railroad tracks. Timeline: June 2016–March 2019 Cost: $27.12 million Funding sources: federal and TxDOT