Upcoming projects
Gosling Road at West Rayford traffic signal
Project: This project will modify the existing signal with a new mast arm traffic signal in order to improve traffic flow and safety along Gosling Road. The Harris County Precinct 3 Commissioner’s Office is overseeing the design work.
Update: Design work is underway for a potential light at the intersection of Gosling Road and West Rayford Road.
- Cost: TBD
- Timeline: early 2027
- Funding sources: Harris County Precinct 3, Texas Department of Transportation
Project: This will make improvements to the intersections of Hufsmith Road at Kuykendahl Road, Stuebner Airline Road and FM 2978.
Update: This project is now in the design phase for future planning and construction, according to Harris County Precinct 3.
- Cost: $36,645
- Timeline: TBD
- Funding source: Harris County Precinct 3
Spring Stuebner Road expansion
Project: This project will expand Spring Stuebner Road from two to four lanes from west of Leitner Lane to the Grand Parkway. Existing drainage and traffic signals will also be improved and added as needed.
Update: Precinct 3 officials said construction on this project is expected to take roughly one year to complete.
- Cost: $8.1 million
- Timeline: Second quarter 2026
- Funding source: Harris County Precinct 3
Project: Between FM 1488 and FM 149, the construction of a hot mix asphalt overlay is taking place on Spur 149.
Update: This project is 90% complete, according to a Nov. 10 media update from TxDOT.
- Cost: $1.1 million
- Timeline: September 2025-fourth quarter 2025
- Funding sources: federal, state funds