Ongoing projects
FM 1488 widening west of Magnolia
Project: Between the Waller County line and FM 1774 west of Magnolia, FM 1488 is being widened from two to four lanes with a continuous left-turn lane.
Update: This project is 98% completed, according to a Sept. 11 media update from the Texas Department of Transportation.
- Timeline: November 2020-third quarter 2025
- Cost: $35.35 million
- Funding source: state funds
Project: FM 1488 is being widened from two to four lanes with a continuous left-turn lane in Magnolia between FM 1774 and west of FM 149.
Update: According to a Sept. 11 media update from TxDOT, this project is 60% completed.
- Timeline: June 2022-third quarter 2027
- Cost: $48.3 million
- Funding source: state funds
Spur 149 overlay
Project: A hot mix asphalt overlay project will take place along Spur 149 between FM 1488 and FM 149.
Update: This project was anticipated to start Sept. 15, according to a Sept. 11 media update from TxDOT.
- Timeline: September 2025-fourth quarter 2025
- Cost: $1.1 million
- Funding sources: federal, state funds