FM 2978 bridge construction to wrap up in third quarter

The Texas Department of Transportation is widening the FM 2978 bridge over Spring Creek. (Courtesy Fotolia)
The Texas Department of Transportation is widening the FM 2978 bridge over Spring Creek. (Courtesy Fotolia)

The Texas Department of Transportation is widening the FM 2978 bridge over Spring Creek. (Courtesy Fotolia)

The Texas Department of Transportation is widening the FM 2978 bridge over Spring Creek from two to four lanes. The project was 74% complete as of March 1, according to TxDOT information.

Timeline: October 2018-third quarter 2020


Cost: $7.6 million

Funding source: TxDOT