Major takeaways
Updates to bond-funded projects include:
FM 2920 Lift Station improvements
- Final easements were approved by Harris County Commissioners Court on Nov. 13.
- The city is awaiting signed documents and recommendations to release the contractor to begin work.
- Phase 2 is at 90% design, and bid is expected to go out in the first quarter of 2026.
- The project remains within budget, with over $7 million available for construction.
- Estimated total project cost: $15.4 million
- Current cost: $8.2 million
- Pending cost (Phase 2): $7.1 million
- Currently in construction and on schedule.
- 18-inch water line installation is underway along South Persimmon Street.
- Well drilling began Nov. 16 and is expected to finish by Dec. 25.
- The project remains within budget; staff is monitoring excess funds.
- Estimated total project cost: $17.7 million
- Significant progress has been made, and concrete work continues through the next month.
- Construction remains on schedule, and all long-lead items have been ordered.
- Backfilling of the ground storage tank foundation ring and other components is underway.
- The project remains within budget.
- Estimated total project cost: $10.6 million
16-inch water line at Hufsmith Road
- The project is ahead of schedule.
- BNSF bore review is scheduled for Dec. 6, which will complete the tie-in for the segment.
- Crews are currently working along Peach Street toward the baseball field with open-trench installation advancing toward Hospital Street.
- The project is under budget, and no change orders are anticipated.
- Estimated total project cost: $1.5 million
- Project budget: $2.5 million
- Construction is complete.
- Final walkthrough, punch list and close-out documentation are underway.
- The project came in on budget.
- Estimated total project cost: $390,803
- The contractor has completed all amenity work.
- The city is awaiting CenterPoint to set meters at five locations to activate pedestal lighting.
- Closeout is expected by the end of December
- Estimated total project cost: $407,314
- Sidewalk construction along Baker Drive is complete.
- A contract for the final section on Cherry Street (Market to Tomball ISD Administration Building) is active.
- Work is expected to finish by the end of November.
- Estimated total project cost: $206,785
- Project officially completed before Sept. 30.
- Final cost: $5.6 million—about $75,000 under budget
FM 2920 reconstruction
- The Texas Department of Transportation design engineer is advancing toward 30% design.
- The city is pursuing a professional services agreement for utility relocations.
- Scope of work is being finalized and the request for proposals is expected in December, with the award anticipated in February.
- Nearly 200 new trees will be purchased, including 50-60 large 10-to-12-inch caliper oaks.
- Trees will undergo a growing period before planting.
- Plantings will occur from Fort Connors to Willow streets, coordinated with TxDOT’s arborist and landscape architect to ensure longevity and avoid conflicts with buildings or future roadway work.

