1. Eclipse on Hufsmith: 18550 Hufsmith Kohrville Road, Tomball
Type of work: new construction
Timeline: June 30, 2022-Oct. 31, 2023
Estimated cost: $21 million
Scope: new multibuilding apartment
2. 403 Eats music venue: 403 E. Main St., Tomball
Type of work: new construction
Timeline: Feb. 1-May 1
Estimated cost: $600,000
Scope: outdoor music venue
3. Sun Auto-Woodlands: 26810 Kuykendahl Road, Tomball
Type of work: new construction
Timeline: March 1-Aug. 31
Estimated cost: $1.3 million
Scope: new auto shop
4. Primespot North Eldridge: 18220 N. Eldridge Parkway, Tomball
Type of work: new construction
Timeline: Feb. 25-Nov. 15
Estimated cost: $450,000
Scope: 12,500 square feet of convenience store and lease space
5. Tomball OR renovation: 605 Holderrieth Blvd., Tomball
Type of work: renovation/alteration
Timeline: March 1-Sept. 12
Estimated cost: $1.4 million
Scope: renovation within the hospital's first floor surgical suite to enlarge one operating room, create two new operating rooms and support spaces as well as modify the doctor lounge and women's locker room
6. LEGENT North Houston Surgical Hospital: 24429 Hwy. 249, Tomball
Type of work: renovation/alteration
Timeline: April 1, 2022-Jan. 31, 2023
Estimated cost: $3 million
Scope: finishing out an existing interior shell space of approximately 8,000 square feet for a hospital surgical suite
7. Mattern Business Park: 22828 Hufsmith-Kohrville Road, Tomball
Type of work: new construction
Timeline: Feb. 15-Nov. 22
Estimated cost: $1.8 million
Scope: construction of four office warehouse buildings and site development work
8. Chase Magnolia Place: FM 1488 at Spur 149, Magnolia
Type of work: new construction
Timeline: April 1-Dec. 31
Estimated cost: $1.5 million
Scope: new construction of bank
9. Dental Office-Dr. Cutbirth: 10584 FM 1488, Ste. 100, Magnolia
Type of work: renovation/alteration
Timeline: March 1-Sept. 30
Estimated cost: $300,000
Scope: interior buildout
10. Heartland Dental: FM 1488 and Spur 149, Magnolia
Type of work: renovation/alteration
Timeline: March 1-July 30
Estimated cost: $127,680
Scope: tenant buildout