Upcoming projects
1. Lake Woodlands Drive at Gosling Road intersection improvements
Project: The project will extend turn lanes from eastbound Lake Woodlands Drive onto northbound Gosling Road. It will also extend turn lanes from westbound Lake Woodlands Drive onto southbound Gosling Road.
Update: Engineering design was complete in early December and utility coordination was ongoing, Precinct 3 officials said.
- Timeline: Construction will begin in early 2026.
- Cost: $40,000 (design)
- Funding source: Montgomery County road bond
Project: The project will extend dual left-turn lanes from westbound Research Forest Drive to southbound Gosling Road. They will also be extended from Gosling Road to Research Forest Drive in both directions.
Update: Engineering design was complete and utility coordination was ongoing as of early December, officials said.
- Timeline: Construction will begin in early 2026.
- Cost: $25,500 (design)
- Funding source: Montgomery County road bond
Project: The project will add a left-turn lane and extend lane storage from northbound Kuykendahl Road to Woodlands Parkway.
Update: Engineering design was complete and new signal equipment was ordered as of early December, Precinct 3 officials said.
- Cost: $88,240 (design)
- Timeline: Construction will begin in spring or summer 2026.
- Funding source: Montgomery County road bond
Project: A traffic signal will be replaced at the intersection of Grogan’s Mill Road and the entrance to the Grogan’s Mill Village Center, according to Precinct 3.
Update: Engineering design was underway and the project was starting the construction planning phase as of early December, officials said.
- Timeline: Construction is slated to begin in summer 2026.
- Cost: $52,500 (design)
- Funding source: Montgomery County road bond
Project: The project will redesign traffic signal and intersection layout, upgrade traffic signal facilities, replace pavement in the intersection as needed and restripe the intersection, Precinct 3 officials said in December.
Update: The project was in the engineering design phase in December.
- Timeline: Construction is estimated to start in the summer.
- Cost: $52,500 (design)
- Funding source: Montgomery County road bond
Project: TxDOT is using the existing right of way on Hwy. 242 between FM 1488 and I-45 to widen lanes and restripe the intersections.
Update: As of the most recent information released by TxDOT in November, the project being carried out by Posillico Civil Inc. was 71% complete.
- Cost: $29.11 million
- Timeline: Oct. 23, 2023-fourth quarter 2026
- Funding sources: federal, state funds
7. Lake Woodlands Drive at East Panther Creek Drive turn-lane extension
Project: The project extended the left-turn lane from westbound Lake Woodlands Drive onto southbound East Panther Creek Drive.
Update: As of a November update, the project was completed.
- Timeline: June-August (design), September-November (construction)
- Cost: $22,500 (design), $116,057 (construction)
- Funding source: Montgomery County road bond
Project: The project extended the left-turn lane to the median opening on northbound Grogans Mill Road and the turn onto westbound Lake Woodlands Drive.
Update: As of a November update, the project was completed.
- Timeline: September-November
- Cost: $22,500 (design), $84,744 (construction)
- Funding source: Montgomery County road bond
Project: The left-turn lane was extended from westbound Woodlands Parkway to southbound Branch Crossing Drive. It also extended a left-turn lane from Branch Crossing Drive onto eastbound Woodlands Parkway.
Update: The project was completed in early December.
- Timeline: fall-December.
- Cost: $58,000 (design), $310,876 (construction)
- Funding source: Montgomery County road bond

