A variety of construction projects are underway in Conroe ISD, including work on new schools across the district. CISD passed a $653 million bond package in 2019 and a $1.8 billion bond package in 2023.

Rob Eissler Elementary School
  • Project: The new elementary school, funded by the 2023 bond, will have a 950-student capacity and serve The Woodlands High School feeder zone.
  • Update: As of July 17, the school is getting furniture and instructional materials for the principal and the administration, said Easy Foster, the district's executive director of planning and construction.
  • Location: 14000 Old Conroe Road, Conroe
  • Timeline: opening for the 2025-26 school year
Mittie J. Campbell Elementary School
  • Project: The new elementary school will have a 950-student capacity in the Oak Ridge and Caney Creek high school feeder zones.
  • Update: Furniture is being installed and instructional materials are being delivered as of mid-July, Foster said.
  • Location: 15895 Stonecrest Drive, Conroe
  • Timeline: opening for the 2025-26 school year
Grand Oaks Junior High School and Ninth Grade Campus
  • Project: The new school will serve seventh, eighth and ninth grades in the Grand Oaks High School feeder zone.
  • Update: As of July 17, masonry walls are being installed following steel erection and roofing on structures including the athletic building.
  • Location: 28075 Woodson’s Grand Drive, Spring
  • Timeline: opening in January 2027
Conroe High School renovations
  • Project: The school is making improvements to its campus to accommodate student growth.
  • Update: The district is working on the middle part of the complex to create a new entrance for the school and to connect the buildings.
  • Location: 3200 W. Davis St., Conroe
  • Timeline: completion anticipated in 2026
Kacy Arnold Elementary School
  • Project: This new elementary school will be located in the Grand Oaks High School feeder zone.
  • Update: Work on this project has begun as of July 17, Foster said.
  • Location: 28378 Sterling Oak Drive, Spring
  • Timeline: opening in August 2026
Janene Fowler Intermediate School
  • Project: This campus, serving fifth and sixth grades, will serve the Conroe and Timber Mill feeder zones.
  • Update: The construction process is on schedule, and the district is negotiating some agreements with the city of Conroe for the building's utility connections.
  • Location: FM 1314 north of Crighton/Creighton Road, Conroe
  • Timeline: opening in August 2026
Lynn Cartwright Junior High School
  • Project: Serving fifth and sixth grades, this campus will serve the Conroe High School feeder zone.
  • Update: The construction process was on schedule and the foundations were under construction as of July 17, Foster said.
  • Location: FM 1314 north of Crighton Road, Conroe
  • Timeline: opening in August 2027
Caney Creek High School ninth-grade campus
  • Project: The ninth-grade campus will have a capacity of 1,600 students.
  • Update: The building is currently under construction with the foundation process underway in July, Foster said.
  • Location: FM 1485 just north of Hwy. 242
  • Timeline: opening in August 2027
Timber Mill High School
  • Project: Timber Mill High School will create a new feeder zone with students from Conroe and Caney Creek high schools.
  • Update: As of July 17, the district was beginning direct structural steel for the building, Foster said.
  • Location: 2700 N. Loop 336 E., Conroe
  • Timeline: December 2024-August 2027