Read about some of the latest updates on transportation projects in the Sugar Land-Missouri City area.
This list is not comprehensive.
1. Industrial Boulevard panel replacement
Project: The road is set to see the replacement of street panels on its northern side following reconstruction to the southern portion in 2018.
Update: At a March 17 meeting, Sugar Land City Council approved a construction contract with Teamwork Construction Services Inc.
- Timeline: completion expected by December
- Cost: $2.27 million
- Funding source: capital improvement program
2. Williams Trace Boulevard reconstruction
Project: The four-lane divided road will be reconstructed from Oyster Creek to Hwy. 6.
Update: At a March 17 meeting, Sugar Land City Council approved a design contract with EHRA Engineering.
- Timeline: April 2026-April 2027 (design); construction expected to begin in July 2027
- Cost: $1.22 million (design)
- Funding source: Fort Bend County
3. Trammel Fresno Road reconstruction
Project: The project aims to widen the roadway and install new concrete pavement as well as add sidewalks.
Update: Missouri City officials said the design phase is nearing completion.
- Timeline: late summer-early 2028 (construction)
- Cost: estimated at $11.7 million
- Funding source: Fort Bend County