Curious as to what new businesses and renovations are underway or coming to Sugar Land and Missouri City? The following projects have been filed in the last two weeks through the Texas Department of Licensing and Regulation. The following information may be subject to change.
1. Chick-fil-A: 2323 Hwy. 6 S., Sugar Land
Type of work: new construction
Timeline: May 16-Oct. 20
Estimated cost: $1.2 million
2. Houston Methodist Sugar Land Hospital: 16655 Southwest Freeway, Sugar Land
Type of work: new construction
Timeline: May 2, 2022-Feb. 28, 2025
Estimated cost: $206 million
3. SurePoint Self Storage: 4121 Sienna Parkway, Missouri City
Type of work: new construction
Timeline: July 1, 2022-Jan. 1, 2023
Estimated cost: $1.88 million
4. Zapvor By Thai Spice: 13517 University Blvd., Ste. 300, Sugar Land
Type of work: new construction
Timeline: March 15-June 15
Estimated cost: $75,000
5. Petco: 10427 Hwy. 6, Missouri City
Type of work: new construction
Timeline: Sept. 1, 2022-Feb. 1, 2023