1. International Skills Barber School: 2420 Cartwright Road, Missouri City
Type of work: renovation/alteration
Timeline: Nov. 15-Dec. 15
Estimated cost: $200,000
2. Rue21: 16535 Hwy. 59, Sugar Land
Type of work: renovation/alteration
Timeline: Jan. 1-March 4
Estimated cost: $250,000
3. Dr. Zeeshan's Clinic: 400 Promenade Way, Ste. 1500, Sugar Land
Type of work: new construction
Timeline: Nov. 15-Jan. 30
Estimated cost: $200,000
4. Memorial Hermann Sugar Land Hospital operating room expansion: 17500 W. Grand Parkway S., Sugar Land
Type of work: renovation/alteration
Timeline: Nov. 22-May 31
Estimated cost: $2.5 million
5. Vibe Nails & Spa: 8027 Hwy. 6 S., Missouri City
Type of work: new construction
Timeline: Dec. 1-March 1
Estimated cost: $120,000