A number of road projects aimed at improving mobility across the Spring and Klein communities are either underway or planned to begin soon. Here are some updates on local projects. This list is not comprehensive.
Upcoming projects
1. Gosling Road at West Rayford traffic signal
Project: This project will modify the existing signal with a new mast-arm traffic signal to improve traffic flow and safety along Gosling Road. The Harris County Precinct 3 commissioner’s office is overseeing the design work.
Update: Design work is underway for a potential light at the intersection of Gosling Road and West Rayford Road.
- Timeline: early 2027
- Cost: TBD
- Funding sources: Harris County Precinct 3, Texas Department of Transportation
2. Hufsmith Road intersection improvements
Project: This will make improvements to the intersections of Hufsmith Road at (A) Kuykendahl Road, (B) Stuebner Airline Road and FM 2978.
Update: This project is now in the design phase for future planning and construction.
- Timeline: TBD
- Cost: $36,645
- Funding source: Harris County Precinct 3
3. Cutten Road extension
Project: According to Harris County Precinct 3 officials, this project will construct a four-lane boulevard from Bavaria Drive to Cossey Road.
Update: Officials said they are now in the design phase to understand the scope of the project.
- Timeline: TBD
- Cost: TBD
- Funding source: Harris County Precinct 3
Ongoing projects
4. Louetta Road asphalt rehabilitation
Project: This project will allow for the asphalt rehabilitation of Louetta Road from Champion Forest Drive to Holzworth Road.
Update: This project is in the design stage, with a potential timeline available soon.
- Timeline: February-May 2026
- Cost: $539,909
- Funding source: Harris County Precinct 3
5. Spring Cypress Road and Louetta Road asphalt rehabilitation
Project: This project will rehabilitate asphalt on Spring Cypress Road, from (A) west of Stuebner Airline Road to east of T.C. Jester Boulevard, and (B) Louetta Road from Old Louetta Road to east of Champion Forest Drive.
Update: Work has begun along Spring Cypress Road to replace asphalt as part of an asphalt rehabilitation effort.
- Timeline: March 2026
- Cost: $6.5 million
- Funding source: Harris County Precinct 3
6. Hargrave Road asphalt rehabilitation
Project: This project will allow for asphalt rehabilitation on Hargrave Road from Hwy. 249 to Falba Road.
Update: Work is underway to make asphalt improvements along Hargrave Road.
- Timeline: March 2026
- Cost: $1.4 million
- Funding source: Harris County Precinct 3
7. Stuebner Airline bridge repairs
Project: This project will repair the bridge portion of Stuebner Airline Road over Cypress Creek near Cypresswood Drive.
Update: Work has begun on the bridge repair along Stuebner Airline Road.
- Timeline: started December 2025
- Cost: $900,000
- Funding source: Harris County Precinct 3
8. Spring Stuebner Road expansion
Project: This project will expand Spring Stuebner Road from two to four lanes from west of Leitner Lane to the Grand Parkway. Existing drainage and traffic signals will also be improved and added as needed.
Update: Precinct 3 officials said construction on this project is expected to take roughly one year to complete.
- Timeline: second quarter of 2026
- Cost: $8.1 million
- Funding source: Harris County Precinct 3