Upcoming projects
Ford Road widening, Segment 2
Project: Ford Road will be widened from two to four lanes between Needham Road and Mills Branch Road; ditches will also be reconstructed along the corridor.
Update: County officials are finalizing engineering and relocation of utilities for this project, said Joshua Pascua, chief of staff for Montgomery County Precinct 4 Commissioner Matt Gray, via email Sept. 11.
- Timeline: Construction expected to begin in the third quarter of 2026
- Cost: TBD
- Funding sources: Montgomery County 2025 Road Bond, Precinct 4 Commissioner's Office, federal funding secured by Rep. Dan Crenshaw
Ford Road widening, Segment 1
Project: Ford Road will be widened from two to four lanes between Hwy. 59 and Needham Road. Ditches will also be reconstructed along the corridor.
Update: Construction is expected to begin in October, Pascua said via email Sept. 11.
- Timeline: September 2025-fourth quarter of 2026
- Cost: $5.9 million
- Funding sources: Montgomery County 2025 Road Bond, Precinct 4 Commissioner's Office
Project: Sorters Road will be widened from two to four lanes between North Bentwood Channel and Northpark Drive. Ditches will also be reconstructed along the corridor.
Update: Construction is expected to begin in October, Pascua said via email Sept. 11.
- Timeline: September 2025-first quarter of 2027
- Cost: $15.6 million
- Funding sources: Montgomery County 2025 Road Bond, Precinct 4 Commissioner's Office
Sorters Road rehabilitation
Project: The existing roadway was reconstructed between River Ridge and Royston drives to address potholes and road base failure.
Update: The project was completed in August before the start of New Caney ISD's 2025-26 school year, Pascua said.
- Timeline: July-August 2025
- Cost: $219,862
- Source: Montgomery County 2025 Road Bond, Precinct 4 Commissioner's Office