Check out the latest information on three road projects in New Caney and Porter, according to an April 10 report from the Texas Department of Transportation's Montgomery area office. This list is not comprehensive.

Ongoing projects

FM 1485 mill and overlay


Project: FM 1485 will be repaired and a new layer of asphalt will be added with new pavement markings and signs along a roughly seven-mile stretch of existing road between Old Houston Road and Kidd Cemetery Road.

Update: Construction was set to begin in the second quarter of 2025, according to an April 10 TxDOT report. The project contractor is Vulcan Materials Asphalt and Construction.
  • Timeline: second quarter 2025-second quarter 2026
  • Cost: $8.8 million
  • Funding source: 80% federal, 20% state
FM 1314 rehabilitation


Project: FM 1314 will be rehabilitated along a roughly two-mile stretch of existing road from Hwy. 242 to north of McQueen Road.

Update: The project was 6% completed, as of an April 10 TxDOT report. The project contractor is R. Civic Construction, LLC.
  • Timeline: first quarter 2025-fourth quarter 2028
  • Cost: $31.4 million
  • Funding source: 80% federal, 20% state
Recently completed

Hwy. 242 widening


Project: Hwy. 242 was widened from two to four lanes from west of FM 1485 to Hwy. 59.


Update: The project was 99% completed, as of an April 10 TxDOT report. The project contractor is James Construction Group.
  • Timeline: Dec. 2, 2019-second quarter 2025
  • Cost: $76.5 million
  • Funding source: 80% federal, 20% state