Phase 2—which is expected to cost $76 million—will consist of a 180,000-square-foot expansion of the campus, according to the email. More classrooms and learning spaces will be added, raising student capacity to about 2,250.
WFHS will also undergo a third phase of renovations, which is slated to be completed by August 2026. This $6.4 million project will add a multipurpose, covered practice facility to the campus.
Phase 1 of the WFHS project wrapped up in 2022 and created a student capacity of 1,500 students. All three project phases are funded under NCISD's $695 million bond package, which was approved by voters in May 2023.