Here's the latest construction updates on four New Caney ISD projects funded by the district's $695 million bond package, which was approved by voters in May 2023.

Highlands Middle School

A new 215,100-square-foot campus will be built by Drymalla Construction.
  • Update: The cost of the project is now $10 million less than originally projected, said Richard Ressler, director of facilities and planning, during an April 21 board of trustees meeting.
  • Timeline: June 9, 2025-April 2027
  • Cost: Less than $60 million
  • Funding source: 2023 bond funds
Highlands Elementary School

A candidate school for the International Baccalaureate Primary Year Program, the campus will accept 50 students per grade level—first through fifth grade—for its inaugural school year.
  • Update: Construction is nearing completion.
  • Timeline: March 2024-July 2025
  • Cost: Less than $44 million
  • Funding source: 2023 bond funds
New Caney High School Career and Technical Education Center

This 50,431-square-foot facility will feature classrooms and shops for agriculture, welding, automotive, construction, architecture and engineering programs.
  • Update: The center will be accepting students for the 2025-26 school year.
  • Timeline: June 2024-summer 2025
  • Cost: $21 million
  • Funding source: 2023 bond funds
New Caney High School extracurricular improvements


Located at New Caney High School, this project consists of multiple phases and consists of upgrades to the school’s athletic facilities, including the football field, track, baseball/softball fields and multipurpose practice facility.
  • Update: This spring, the baseball and softball fields were used by the school’s teams for the first time.
  • Timeline: June 2024-summer 2025 (softball/baseball fields); summer 2025-fall 2026 (football field and track)
  • Cost: $32 million (softball/baseball fields); $21 million (football field and track)
  • Funding source: 2023 bond funds