For more Harris County Precinct 3 infrastructure projects, click here.
Recently completed
1. Atascocita Road restriping
Project: This maintenance project restriped Atascocita Road from Old Humble Road to just south of FM 1960.
Update: This project has been completed.
Timeline: Completed in the fourth quarter of 2023
Cost: $200,000
Funding source: Harris County Precinct 3
2. Will Clayton Parkway sidewalk installation
Project: A 500-foot section of sidewalk was installed on the south side of Will Clayton Parkway from Cricket Mill Drive to Woodland Hills Drive. The project provides a safe route to and from schools, directing pedestrians to a signalized intersection.
Update: This project has been completed.
Timeline: Completed in the fourth quarter of 2023
Cost: $50,000
Funding source: Harris County Precinct 3
Upcoming projects
3. West Lake Houston Parkway Sidewalk, Phase 1
Project: Sidewalks will be constructed on both sides of West Lake Houston Parkway from Madera Run Parkway to Aerobic Avenue. The project aims to enhance pedestrian mobility in the area.
Update: This project is in the design phase.
Timeline: Estimated completion by the first quarter of 2025
Cost: TBD
Funding source: Harris County Precinct 3
4. West Lake Houston Parkway/Will Clayton Parkway sidewalk, Phase 2
Project: A sidewalk will be constructed on West Lake Houston Parkway from Aerobic Avenue to FM 1960 and on Will Clayton Parkway from Aerobic Drive to Garabit Drive. The project aims to enhance pedestrian mobility in the area.
Update: This project is in the design phase.
Timeline: Estimated completion by the fourth quarter of 2025
Cost: TBD
Funding source: Harris County Precinct 3