A project to expand Northpark Drive from four to six lanes between Hwy. 59 and Russell Palmer Road and add an overpass over the railroad went out to bid on Aug. 17 with construction expected to begin shortly after. According to Ralph De Leon, administrator of the Lake Houston Redevelopment Authority and Tax Increment Reinvestment Zone 10, the project is expected to take roughly 30 months to complete once construction begins.

Timeline: September 2022-March 2025

Cost: $52 million

Funding sources: LHRA, TIRZ 10, city of Houston