A joint project from Harris County precincts 1 and 2 and Humble ISD to extend Timber Forest Drive south of Madera Run Parkway to Lakewood Pines Boulevard began in late December. The project will create a four-lane bridge over the Union Pacific Corp. railroad with a median and sidewalks. It will also create a thoroughfare to HISD’s Centennial Elementary School, which is located at the corner of Timber Forest Drive and Lakewood Pines. Construction will wrap up in late 2021.
Timeline: Dec. 30, 2020-late 2021
Cost: $7.64 million
Funding sources: Harris County precincts 1 and 2, Humble ISD
Correction: The original version of this story incorrectly stated the project would wrap up in May or June. The project is expected to be completed in late 2021.