The Goddard School—Lake Hill Farm Way, Fulshear
Type of work: new construction
Timeline: Construction expected to start Oct. 1
Estimated cost: $2 million
Reliant ABA Therapy—24210 Cinco Terrace Drive, Katy
Type of work: renovation/alteration
Timeline: Start date of Oct. 30, completion date of Dec. 15
Estimated cost: $150,000
Scope of work: Modify current gymnasium into office space; new lounge/kitchen; minor existing office modifications
Kizuki Ramen and Izakaya—23220 Grand Circle Blvd., Ste. 140, Katy
Type of work: renovation/alteration
Timeline: Start date of Oct. 1, and estimated completion date of Feb. 1, 2022
Estimated cost: $500,000
Scope of work: New restaurant in an existing building
Livik Nail—3011 W. Grand Parkway N., Ste. 700, Katy
Type of work: new construction
Timeline: Start date Sept. 20, completion date of Nov. 30
Estimated cost: $50,000
RTIC Fulfillment Center—3900 Peek Road, Katy
Type of work: renovation/alteration
Timeline: Sept. 21 start date, Jan. 31, 2022 completion date
Estimated cost: $2 million