The details
The scope of work for the Addicks Repair Package Two project entails:
- Repairs to channels where erosion and slope failures have occurred
- Repairs of concrete structures and storm outfall failures
The construction is expected to be complete by winter 2023 or 2024. The cost for the second repair package is estimated to be $2.1 million.
Residents in the neighborhoods surrounding the following areas will begin to see increased construction activity, according to the release:
- Bear Creek
- Langham Creek
- South Mayde Creek