Harris County Precinct 3 has several road projects planned for the Cy-Fair area. See additional details below.
1. Greenhouse Road bridge project: Harris County Precinct 3 will construct a two-lane northbound bridge over Cypress Creek to improve safety and capacity.
- Cost: $6.5 million
- Timeline: construction to begin in second quarter 2024
- Funding source: Harris County Precinct 3
2. Cypress North Houston Road widening: Crews will replace the two-lane asphalt Cypress North Houston Road with a four-lane concrete boulevard with a raised median from Perry Road to Jones Road. New or upgraded traffic signals will also be added at Autumn Mills Road, Misty Moss Lane and Jones Road.
- Cost: $7.5 million
- Timeline: construction to begin in third quarter 2024
- Funding source: Harris County Precinct 3
3. Huffmeister Road sidewalk project: A 5-foot sidewalk will be installed from Fleur de Lis Boulevard to north of Cypress North Houston Road on the east and west sides of Huffmeister Road for improved pedestrian safety.