Upcoming projects
1. I-45 high-occupancy vehicle extension
Project: Between FM 1488 and South Loop 336, I-45 will undergo a high-occupancy vehicle lane extension.
Update: This project was set to begin in the first quarter of 2025, according to an April 17 media update from the Texas Department of Transportation.
- Timeline: first quarter 2025-fourth quarter 2025
- Cost: $1.3 million
- Funding sources: federal, state funds
Project: Hwy. 75 will undergo improvements such as underseal base repair and planing between South Loop 336 North and Gladstell Street.
Update: This project was set to begin in the first quarter of 2025, according to an April 17 media update from TxDOT.
- Timeline: first quarter 2025-fourth quarter 2025
- Cost: $3.3 million
- Funding source: state funds
3. I-45 direct connector
Project: A direct connector will be installed along I-45 between Shenendoah Park Drive and Hwy. 242, connecting northbound I-45 with eastbound Hwy. 242.
Update: This project was 1% complete as of an April 17 media update from TxDOT.
- Timeline: second quarter 2025-second quarter 2028
- Cost: $42.63 million
- Funding sources: federal, state funds
Project: Along South Loop 336 between I-45 and Sgt. Ed Holcomb Boulevard, safety lights, conduits, conductors and other electrical services are underway.
Update: According to an April 17 media update from TxDOT, this project is 96% completed.
- Timeline: December 2024-third quarter 2025
- Cost: $518,164
- Funding source: state funds
Project: Between 10th Street and South Loop 336, Hwy. 105 is being widened from two to four lanes.
Update: According to an April 17 TxDOT media update, this project is 44% complete.
- Timeline: March 2023-second quarter 2028
- Cost: $52.7 million
- Funding source: state funds
Project: South Loop 336 is being widened from two to four lanes with a continuous left-turn lane, between I-45 and Ladera Creek Trace.
Update: This project is 12% completed, according to an April media update from TxDOT.
- Timeline: November 2024-third quarter 2027
- Cost: $20.6 million
- Funding source: state funds
Project: Hwy. 105 is being reconstructed and widened from two to four lanes between South Loop 336 and FM 1484.
Update: According to an April 17 media update from TxDOT, this project is 98% completed.
- Timeline: February 2023-third quarter 2025
- Cost: $90.81 million
- Funding source: state funds
Project: High mast LED poles are being installed along the mainlanes of I-45 between FM 830 and Shepard Hill Road.
Update: This project is 30% completed, according to an April 17 media update.
- Timeline: February 2025-first quarter 2026
- Cost: $1.45 million
- Funding source: state funds
Project: TxDOT is using an existing right of way on Hwy. 242 between FM 1488 and I-45 to widen lanes and restripe the intersections.
Update: According to an April 17 media update from TxDOT, the project is 54% complete.
- Timeline: October 2023-fourth quarter 2026
- Cost: $29.11 million
- Funding sources: federal, state funds