There are several transportation projects underway in the Conroe and Montgomery area. Check out their progress below. This list is not comprehensive.

1. Hwy. 105 widening

Project: This project is reconstructing and widening Hwy. 105 in Conroe from two to four lanes between 10th Street to South Loop 336.

Update: A March media update from the Texas Department of Transportation shows this project is 22% complete.

  • Timeline: March 2023-third quarter 2027
  • Cost: $51.83 million
  • Funding source: state funds

2. Hwy. 242 widening

Project: This project is widening Hwy. 242 between I-45 and FM 1488.



Update: According to a March media update from TxDOT, this project is 12% completed.

  • Timeline: October 2023-first quarter 2026
  • Cost: $28.67 million
  • Funding sources: federal, state funds

3. Hwy. 105 reconstruction

Project: Hwy. 105 is being reconstructed and widened from two to four lanes between South Loop 336 and FM 1484.

Update: This project is 45% complete, according to a March media update from TxDOT.

  • Timeline: October 2022-third quarter 2027
  • Cost: $88.47 million
  • Funding source: state, federal funds

4. FM 1486 repairs

Project: FM 1486 is undergoing overlay and base repairs between Hwy. 105 and FM 1774.



Update: This project is 6% completed, according to a March media update from TxDOT.

  • Timeline: October 2023-third quarter 2024
  • Cost: $4.57 million
  • Funding source: state funds