Montgomery ISD is underway with a variety of different projects, including the construction of a new CTE and agricultural center. See the latest updates below.

Career and Technical Education, Agriculture Science centers

Project: The $82.92 million spaces will measure a combined 189,000 square feet and feature a bistro operated by culinary students, an engineering and robotics lab and an animal show arena.

Update: Construction is ongoing, district officials said July 18.
  • Location: Along Lone Star Parkway between Buffalo Springs and Plez Morgan drives
  • Timeline: early 2024-targeted completion by July 2025
Lake Creek High School

Project: This $27.88 million project will add capacity for 900 more students and includes an added wing of classroom and lab spaces alongside an additional parking lot.


Update: The expansion is anticipated to be completed in time for the 2024-25 school year, district officials said July 18.
  • Location: 20639 FM 2854 Road, Montgomery
  • Timeline: May 2023-completed this summer
Creekside Elementary

Project: The district's seventh elementary school cost around $43.49 million to build.

Update: A ribbon-cutting event was held at the school the week of August 12, district officials said July 18.
  • Location: behind Lake Creek High School off FM 2854
  • Timeline: May 2023-completed this summer
Montgomery High School

Project: Renovations for the $26 million project include painting classrooms, replacing the main campus roof and replacing the structured cabling in the ninth-grade campus.


Update: Construction on this project is ongoing, district officials said July 18.
  • Location: 22825 Hwy. 105, Montgomery
  • Timeline: Spring 2024-targeted completion summer 2025