Check out three road project updates in League City.
Completed project
League City Parkway right-turn lane
Project: An eastbound right-turn lane was designed west of Butler Road to west of the I-45 southbound frontage road, and tied to the Texas Department of Transportation’s right-turn lane, according to city officials.
Update: The project is complete and the roadway is now open to traffic.
- Timeline: completed in March
- Cost: $2.08 million
- Funding source: Galveston County bond funds
Ongoing project
FM 518 at Country Lane intersection improvements
Project: This is a full intersection rebuild at FM 518 and Country Lane, including signal upgrades, mast arm installation and safety enhancements, according to city officials.
Update: Construction started in late April due to a wait on signal equipment.
- Timeline: slated to wrap in the fall
- Cost: $504,000
- Funding sources: city reinvestment funds
Upcoming project
Traffic signal at Lawrence Road and Village Way
Project: The project scope includes a design and rebuild of the traffic signal at the intersection, according to city officials.
Update: Construction is slated to begin in May.
- Timeline: estimated to take a year to complete, varies depending on delivery of new signal apparatus
- Cost: $573,000
- Funding sources: city reinvestment funds