Update: Work is currently ongoing.
- Timeline: project expected to be done by end of October 2026
- Cost: $6.12M
- Funding source: city's reinvestment fund
FM 518 at County Lane intersection improvementsProject:
The project includes replacing the area’s span wire traffic signals with signals on poles, as well as improving the pedestrian crossing bridge and making the area’s signals more resilient to storms.
Update: The project was awarded in August 2025.
- Timeline: contract calls for 320 days to complete, with work expected to wrap in fall 2026 due to long wait on signal equipment
- Cost: $504,000
- Funding source: city’s reinvestment fund
Upcoming projectLeague City Parkway and Walker Street intersection improvements