The I-35 main lanes north of Williams Drive in Georgetown will close nightly Oct. 19-20 to allow crews to set bridge beams for the Northwest Boulevard bridge, a release from the city said.
Starting at 10 p.m. Oct. 19, one northbound I-35 main lane and the Williams Drive entrance ramp will close to traffic. As beams are being placed, all northbound main lanes will close to traffic for 20-minute intervals. Work is expected to be complete by 5 a.m. All work is weather permitting.
At 10 p.m. on Oct. 20, the southbound I-35 main lanes will close, and all traffic will detour to the southbound I-35 frontage road at the Williams Drive exit. Southbound I-35 will reopen to traffic by 5 a.m.
On the night Oct. 21 between 10 p.m. and 5 a.m., the I-35 southbound frontage road will close intermittently to allow for beam placements.