“That's a lot of money to spend, basically, on a package plant that has a couple year solution,” City Manager David Morgan said. “Our goal is to come up with a plan for them to be able to tie into our wastewater system. We think that's a better and safer way to go long term.”
Morgan said staff is working on the sizing and timing of the future Northlands plant, which could also service Heirloom Georgetown. Council member Shawn Hood said he wouldn’t want to see an off-site sewer treatment system adjacent to the floodplain area.
Hood said he approved of the land plan, as long as the primary entrance into the development connects to the proposed traffic signal. Before waiving development standards entirely, as PulteGroup officials proposed, Hood said he’d like to understand PulteGroup’s vision for the subdivision better.
Council members suggested Atkinson Ranch should be more in-line with several standards outlined in the city's MUD policy.